Kazakhstan carries out 350 major road works in 2020

By bne IntelIiNews January 22, 2021

Kazakhstan carried out 350 major road works in 2020 at a total cost of $565mn, World Highways reported.

Repairs were carried out on 3,221km of local roads, while 541km of highways were upgraded. Around 75% of local roads were now in a “good condition” in Kazakhstan, compared to 71% in 2019.

Further upgrades to roads are expected in 2021.

One project involves the development of a highway connecting the commercial capital Almaty with neighbouring Kyrgyzstan. The Asian Development Bank-supported (ADB-supported) project is still under consideration as options for the shorter routes require a drastic increase in costs due to the construction of tunnel sections of either 14.6km, 16km or 12km.

Related Articles

USAID and Kazakhstan launch five year $39mn regional energy programme for Central Asia

The US government via the US Agency for International Development (USAID) in partnership with the Kazakh Ministry of Energy has launched a five-year and $39mn regional energy ... more

EBRD’s regional small business programme records 10,000 participants to date

Over 10,000 financiers in Kazakhstan, Kyrgyzstan, Tajikistan and Uzbekistan have participated in the Regional Small Business ... more

EDB to fund new KAMAZ plant in Kazakhstan

The Eurasian Development Bank (EDB) is set to provide a five-year loan facility for a total of RUB12bn (€135mn) to set up production of axle drives and a foundry in an ... more

Dismiss